Thursday, 30 November 2017

Creative Journey - Progress Report (November)


After researching into existing products I decided begin my ideas process by mind mapping all the potential ideas deciding what ideas were realistic in regards to locations, casting etc. Following the mind mapping ideas I selected the song ‘Sign On’ by Rat Boy. I then analyzed the codes and conventions of this song and video enabling me to develop my ideas for my own production.

Before continuing with my ideas I had to consider the regulation and copyright issues that could potentially restrict my production. I then attempted to get into contact with the record label to request permission to use the song. Whilst awaiting a reply I continued to plan my production including audience research, storyboarding, casting and more. I also carried out a risk assessment to highlight any risked that may occur whilst filming and a production plan to ensure the filming process is organised and effective.

I then performed a final proposal making everyone aware of my plans regarding locations, the theme and more, for the production including audience feedback to gain my peers opinions on how to better my production. After pitching my final proposal I began filming with my cast in a variety of locations. I am yet to begin editing my production but have planned to include that into the production schedule.

Monday, 20 November 2017

General Hazard & Risk Assessment

Assessed by:                                     Tilly Wellard
Date of Assessment:                       20th November 2017 (20/11/17)



Severity (Hazard Classification)
Probability
Risk Level
1 – None
1 – Extremely unlikely
L - Low
2 – Minor Injury
2 – Very unlikely
M - Medium
3 – Major Injury
3 - Unlikely
H - High
4 - Severe
4 – Likely

5 - Death
5 – Very Likely











 
Hazard
Risk Control
S
P
Risk Level
Further information and action required

Weather
Wear appropriate clothing for the duration of the day.

2

3

Low
If the weather consists of sun wear sun protection, if the temperature cold ensure cast and crew wrap up.

Time Pressure
Allow enough time to complete filming.

2

1

Low
People are more likely to take risks and miss hazards when rushing to finish the production.

Tripping
Move or tape down cables and objects that could be tripped over.

2

2

Low
Also allow the camera operator to be comfortable with their route when filming to prevent tripping hazards.


Food
Ensure cast and crew have highlighted any allergies and purchase consumed items from reliable sources.


3


4


Medium
Allow cast and crew to have several breaks to refresh and hydrate with reasonable time frames allowing them to consume food and drink without being rushed.

Stunts (skaters)
Ensure skating cast is aware of the risks involved and wear protective gear.

4

4

High
Allow only experiences and professional skaters to participate and ensure the skateboards are safe. If an accident does occur ensure the crew has the correct numbers to contact.

Anti social behaviour
Brief all individuals that they must act accordingly and unacceptable behaviour will not be tolerated.


1


2


Low
Consider that local citizens that will be located around filming and ensure they are not captured but do not aggravate the public or the cast and crew to avoid conflict and anti social behaviour.
















































In the event of an emergency the following near by contacts are available:

Fire Department (999)
Tamworth Mercia Community Fire Station
81 Lichfield St, Tamworth, B79 7QL

Ambulance Service (999)
Sir Robert Peel Hospital (01827 566333)
Plantation Ln, Mile Oak, Tamworth, B78 73NG

Police Department (999)     
Tamworth Police Station (0300 123 4455)
Spinning School Ln, Tamworth, B79 7BB

Landau Forte Academy Sixth Form (01827 301820)
Ashby Rd, Tamworth, B79 8AA

Friday, 17 November 2017

Production Schedule




Schedule #1 - Landau Forte Academy Sixth Form


Date, Time and Location
24/11/17 @ 12:00
Landau Forte Academy Sixth Form
Cast
Millie McIntosh, Callum Byrne & Rosie Carver
Film Plan
Shot 4, Shot 5, Shot 6 & Shot 40
Equipment
Camera, Tripod & iPhone 7
Props and Costume
No props required, casual clothing required








 

Schedule #2 – Birmingham City Centre


Date, Time and Location
25/11/17 @ 11:00
Birmingham City Centre

 Cast
Olly Burrows, Katie Goodfellow, Georgette Fischer, Callum Byrne, Phoebe Hughes and Millie McIntosh.
Film Plan
Shot 8, Shot 10, Shot 16, Shot 24, Shot 38
Equipment
Camera, iPhone 7
Props and Costume
No props required, casual clothing required

 
Schedule #3 – Graffiti Tunnel, Tamworth
 
Date, Time and Location
26/11/17 @ 12:00
Graffiti Tunnel, Tamworth
Cast
Olly Burrows
Film Plan
Shot 12, 15 & 33
Equipment
Camera, Tripod, iPhone 7
Props and Costume
No props required, casual clothing required



Schedule #4 – Skate Park, Tamworth


Date, Time and Location
26/11/17 @ 14:00
Skate Park, Tamworth
Cast
Olly Burrows & extra skating cast
Film Plan
Shot 26, Shot 27, Shot 28, Shot 29 & Shot 37
Equipment
Camera, Tripod, iPhone 7
Props and Costume
Skateboard and BMX required, casual clothing required


 Schedule #5 – Skate Park, Tamworth


Date, Time and Location
2/12/17 @ 12:00
Skate Park, Tamworth
Cast
Louis Crookes & extra cast
Film Plan
Shot 13, Shot 14, Shot 20, Shot 21, Shot 34 & Shot 36.
Equipment
Camera, Tripod, iPhone 7
Props and Costume
Skateboards required, casual clothing required


 
Schedule #6 – Job Centre, Tamworth

Date, Time and Location
6/12/17 @ 13:00
Job Centre, Tamworth
Cast
Olly Burrows
Film Plan
Shot 17, Shot 18, Shot 30
Equipment
Camera, Tripod, iPhone 7
Props and Costume
No props required, casual clothing required



Schedule #7 – Bus Stop, Tamworth

Date, Time and Location
6/12/12 @ 14:30
Bus Stop, Tamworth
Cast
Olly Burrows
Film Plan
Shot 22
Equipment
Camera, Tripod, iPhone 7
Props and Costume
No props required, casual clothing required


Schedule #8 – Tamworth Police Station

Date, Time and Location
6/12/12 @ 15:00
Police Station
Cast
Olly Burrows
Film Plan
Shot 23
Equipment
Camera, Tripod, iPhone 7
Props and Costume
No props required, casual clothing required


Schedule #9 – Home

Date, Time and Location
11/12/17 @ 12:00
Home
Cast
Tilly Wellard
Film Plan
Shot 35
Equipment
Camera, Tripod, iPhone 7
Props and Costume
Guitar required, casual clothing required


Schedule #10 – Namco Arcade, Tamworth

Date, Time and Location
11/12/17 @ 16:00
Namco Arcade, Tamworth
Cast
No cast required
Film Plan
Shot 19
Equipment
Camera, Tripod
Props and Costume
Penny/Coin Pusher required


Schedule #11 – Car Park, Landau Sixth Form


Date, Time and Location
15/12/17 @ 15:00
Car Park
Cast
Olly Burrows
Film Plan
Shot 39
Equipment
Camera, Tripod, iPhone 7
Props and Costume
Car required, casual clothing required


Evaluation : How did you use media technologies in the construction and research, planning and evaluation stages?